ODOT projects the reopening of all lanes on I-471 by March after fire damage, with critical repair efforts underway.
Repairs for the Daniel Carter Beard Bridge are expected to be complete in March 2025 pending several factors, according to ...
The cause of the fire is still being investigated, CFD added. I-471 Bridge Repairs. Demolition on the I-471 bridge won’t ...
The Daniel Carter Beard Bridge on Interstate 471 was damaged after a fire at the Sawyer Park playground located under the ...
The portions of the Daniel Carter Beard Bridge deck most significantly damaged by fire will be removed and replaced.
There are no reports of injuries. Interstate 471 remains closed at 9 a.m., almost six hours after the fire was first reported. Pete Rose Way is also shut down under the bridge. Traffic on the Ohio ...
Installation of the second round of shoring towers began Monday after the concrete foundation cured over the weekend on the Interstate 471 bridge connecting Ohio and Kentucky, known colloquially ...
CINCINNATI (WKRC) - While Interstate 471 will be closed at the Daniel Carter Beard Bridge following a Friday morning fire, another Cincinnati interstate is set to be closed for pre-planned ...
The Daniel Carter Beard Bridge and both sides of Interstate 471 over the Ohio River are shut down for the morning commute after a massive fire and reports of explosions early Friday. First responders ...
The Daniel Carter Beard Bridge and both sides of Interstate 471 over the Ohio River are shut down for the morning commute after a massive fire and reports of explosions early Friday. First ...